Overview:

  • Michigan regulators issue permits allowing Oracle and OpenAI data center project to destroy 9 acres of wetlands and install 15 diesel backup generators.
  • State granted waiver in October for installation of generators, three months before final permits were approved.
  • The data center is expected to discharge 34.86 tons per year of nitrogen oxides, its largest source of air pollution.

Michigan regulators granted air and wetland permits for Oracle and OpenAI’s $7-billion Saline Township data center in January, allowing for the destruction of around 9 acres of wetlands and the installation of 15 diesel backup generators.

The Michigan Department of Environment, Great Lakes, and Energy (EGLE) issued a permit waiver to data center developer Related Digital Oct. 17, 2025 to begin installation of the generators, roughly three months before the final air quality permit was issued.

The developer applied for the waiver Sept. 24, 2025 to “begin installation of Project Mitten,” referring to the data center, according to the state document. 

The Saline Township board voted against rezoning land for the development in September, then agreed to a settlement the following month after the township was sued by landowners and the developer.

On Dec. 18, the Michigan Public Service Commission granted DTE Energy’s application for quick approval of its contracts for the data center. The lack of a formal approval process and numerous redactions in the electric contracts sparked a public backlash that included multiple protests

Planet Detroit contacted EGLE and Related Digital for comment on this story.  

Nitrogen oxides are data center’s largest air pollution source

The EGLE air quality permit issued Jan. 13 allows for the installation of 14 diesel backup generators and one diesel firewater pump for use during fire emergencies.

The nitrogen oxides, carbon dioxide, volatile organic compounds, fine particulate matter, and other pollutants emitted by the generators fall below the threshold for major pollution sources, according to an EGLE project evaluation

The data center is expected to discharge 34.86 tons per year of nitrogen oxides, its largest source of air pollution. The major source threshold for NOX is 250 tons per year.

The project will require backup generation for approximately 1% of the data center’s total power load, according to a document submitted by developers. 

The project’s 1.4-gigawatt power demand is equivalent to the amount of electricity needed for more than 1 million homes

Data center’s wetlands, Saline River impacts

Residents expressed concern about the project’s impact on the Saline River at a December hearing, saying wetlands are important for protecting local water quality, and the data center’s cooling system could contaminate local waterways.

Related Digital has storage tanks designed to catch any leaks from the data center’s closed-loop cooling system, and the liquid would be taken offsite, Jonathan Furman, the company’s vice president, said at the December hearing.        

The wetlands permit, issued by EGLE on Jan. 16, allows developers to temporarily disturb a stream and install a culvert, and construct three stormwater structures that will discharge into the Saline River, Bridgewater Drain, and an unnamed stream.

Two outflows will be placed in the Saline River’s 100-year floodplain. A wastewater treatment outfall will discharge treated wastewater into the Saline River.

The developer will acquire 13.68 acts of wetlands in the River Raisin Watershed to mitigate the loss of 9.12 acres of wetlands at the data center site.

MORE SALINE DATA CENTER NEWS

Brian Allnutt is a senior reporter and contributing editor at Planet Detroit. He covers the climate crisis, environmental justice, politics and open space.